The Association's reserve fund, funding plan, and scheduled reserve projects.

Cash Position

As of September 30, 2026

Reserve account$475,694.00

Reserve cash from the Association's general ledger (reserve account and two CDs), as reported in the 2027 budget mailing of November 2, 2026.

Reserve Fund

Projected as of December 31, 2027

Reserve balance$510,338.00
Fully funded balance (reserve study)$805,315.00
Percent funded63%

The fully funded balance is the amount the reserve study calculates the Association should have on hand, based on the age, remaining useful life, and replacement cost of each component. Percent funded compares the reserve balance to that amount.

Source: 2027 budget mailing, November 2, 2026, based on the 2026 reserve study update by Complex Solutions Ltd. (site inspection June 30, 2026; prepared August 19, 2026). Projections are before interest. The fully funded figure is the Board's adjusted estimate; the study's unadjusted figure is $933,443 (55% funded). The full study is on the Documents page.

Funding Plan

Following the reserve study

PlanMonthlyAnnual
Current reserve contribution
2027 budget adopted by the Board October 14, 2026 (up from $10,000 per month in 2026)
$12,071.00$144,857.00
Recommended by the reserve study, 2027$12,000.00$144,000.00

The Board adopted the reserve contribution recommended by the 2026 reserve study. The study recommends the contribution increase 4% per year for five years and 3% per year after that, and projects the reserve fund would reach full funding over the long term under that plan.

The buildings were repainted in early 2026. The study schedules the stucco repaint ($160,160) for 2028, so the Board removed it and reduced the fully funded balance by $128,128, to $805,315. On that basis the reserve fund is projected to be about 63% funded at December 31, 2027, approximately $294,977 below fully funded.

The Board has not determined that a special assessment is necessary and does not currently anticipate one, provided reserve contributions continue at the levels the study recommends.

Scheduled Reserve Projects, 2027 to 2029

DueComponentEst. costStatus
2027Clubhouse Furniture - Replace$10,500.00Scheduled
2027Clubhouse HVAC Systems - Replace$16,500.00Scheduled
2027Clubhouse Water Heater - Replace$1,500.00Scheduled
2027Concrete - Repair/Replace$6,500.00Scheduled
2027Drinking Fountain - Replace$1,250.00Scheduled
2027Fitness Equipment - Replace$13,000.00Scheduled
2027Mailboxes - Replace$17,500.00Scheduled
2027Patio Decks - Reseal/Repair$12,963.00Scheduled
2027Pool - Resurface$19,000.00Scheduled
2027Pool Deck - Seal/Paint/Repair$3,500.00Scheduled
2027Pool Furniture - Replace$8,000.00Scheduled
2027Pool Heater - Replace$5,000.00Scheduled
2027Spa - Resurface$6,000.00Scheduled
2027Spa Filter - Replace$2,000.00Scheduled
2027Spa Heater - Replace$5,000.00Scheduled
2027Water Feature - Refurbish$12,000.00Scheduled
2028Carpeting - Replace$4,940.00Scheduled
2028Fire Protection System - Renovate$79,040.00Scheduled
2028Pitched Roofs, Tile - Replace$160,160.00Scheduled
2028Red Curbs and Hydrants - Repaint$3,380.00Scheduled
2028Stucco Surfaces - Repaint$160,160.00Completed
Buildings repainted in early 2026; the Board removed the 2028 repaint from the schedule
2029Gas Barbecues - Replace$8,112.00Scheduled
2029Interior Surfaces - Repaint$3,786.00Scheduled
2029Pool and Waterfall Pumps - Replace$3,353.00Scheduled

Due years and estimated costs are from the reserve study (2027 in current dollars; 2028 and 2029 adjusted for 4% inflation). The 2027 total is $140,213, as itemized in the 2027 Reserve Budget. Status is updated by management.

Owners may request the Association's financial statements and budget with a Document Request, or ask a question with an Accounting Question.